At this massive green field of Aluminium Smelter Project , all contracts were very large ; Phase - I - 5,00,000 TPA with320 KA POTs (608 nos) , Phase – II - 12,50,000 TPA with 340 KA Pots (1340 nos).The delivery schedules were the stiffest.
It was here that we learnt to reach the mile stones on the toughest terrains. The photographs and table will provide a glimpse.
The site was extremely demanding. It is here that we learnt to dream big and to achieve the impossible.
In Vedanta Jharsuguda Phase -I the following jobs have been awarded
|
Jobs Executed |
Quantity |
Period |
Pot Shell,Pot Superstructure & Anode Beam |
304 sets |
2006-2008 |
Anode Stem Assembly |
304 Pots |
2006-2008 |
Aluminium Bus bars, Plates & Flexible |
13441 MT |
2006-2008 |
Erection & Commissioning of PTM |
16 nos |
2006-2008 |
FTA |
4 nos |
2006-2008 |
Rail erection & commissioning of PTM & FTA |
15315 RM |
2006-2008 |
In Vedanta Jharsuguda Phase -II the following jobs have been awarded
|
Job executed |
Quantity |
Period |
Pot Shell,Pot Superstructure & Anode Beam |
504 sets |
2008-2010 |
Erection,Installation & Commissioning of PTM FTA
|
30 nos 9nos |
2008-2010 |
Fabrication, Erection, Installation & testing of Busbars & Machining & Assembly of Anode Stem Assembly work
|
336 Pots |
2008-2010 |
Fabrication of Aluminium Bus Bars, Plates & Flexibles & Aluminum Riser |
21048 MT |
2008-2010 |
Rail erection & commissioning of PTM & FTA |
17242 RM |
2008-2010 |
|
|